Kmart distribution centre
March 2021
CoGri Australia Pty Ltd engaged Eifers™ to deliver repair works for Kmart distribution centre in Melbourne. These time-critical works consisted of saw cutting, removing existing deteriorated concrete pavement, excavating poor subgrade, dowel drilling, steel reinforcement and replacing with High Early Strength Concrete (HESC), utilising our Bay-Lynx Manufacturing Inc. volumetric concrete batching unit. The works were completed in 6 hrs allowing the pavement to be trafficable within one hour after pouring, providing minimal impact on the client’s daily operations.