APAM – ARFF Pavement Reconstruction
Client: Melbourne Airport
Main Contractor: Eifers Civil
Timeline: 11 Nov - 18 Nov 2024
PROJECT OVERVIEW:
Profiled approx. Area 3600m2 @ 250mm deep of the existing road surface. Excavate and remove the existing roundabout. Eifers successfully completed these works in a 7 day time frame.
Foam Bitumen Base (FBB) Application: Laid FBB in two layers, each 100mm thick, to create a flexible, durable base layer resistant to cracking and heavy traffic loads. Installed a 50mm layer of Greenpave asphalt, providing a sustainable and high-performance durability.